CONSTRUCTION UPDATE

 

Work is streaming ahead, and the site has been a hive of activity.

Basement levels are now complete and in ground services have been installed.

The ground floor slab is due to be poured this week which will see above ground commence by the end of July.

Despite heavy rain events and yet another COVID 19 lockdown the team is confident of picking up these delays throughout the rest of the program and the projects is still on target for completion Q2 2022.