Construction is currently moving a little slower on site compared to this time last month. The window shop drawing process taking a lot longer than expected but will be resolved in the coming week.

Services such as electrical, plumbing, mechanical and fire are well advanced into the rough-in phase.

Level 2 rough-in has commenced and the roof decking has been fully installed.

Ceiling grid has been fully installed to ground level.

At this stage construction completion of your apartment is anticipated to occur in late November 2019.

Please note that the above anticipated timing is subject to favourable conditions or unforeseen delays. We will continue to provide you with regular construction updates leading up to settlement.