With the weather starting to warm up, we are excited to let you know of the current status of works onsite;
– The concrete structure has been completed.
– The structural steel and roofing has been completed.
– Window installation is nearing completion.
– Joinery has commenced being installed to ground floor apartments.
– Tiling has commenced to ground floor apartments.
Anticipated construction completion of your apartment is still on track for March 2020.
We will ensure to keep you updated as construction progresses.
Please do not hesitate to contact Katrina on 03 8582 8975 or email katrina@settlement-solutions.com.au if you have any queries about your upcoming settlement