Construction is underway at Halcyon with the first pile drilled on the 18th of February.
Piling on the southern boundary is almost complete and the bulk excavation will commence in approximately 4 weeks. This involves drilling through 4 meters of rock.
The builders hope to have completed the full excavation by Mid June 2019.
At this stage construction completion of your apartment is anticipated to occur in mid 2020.
Please note that the above anticipated timing is subject to favourable conditions or unforeseen delays. We will continue to provide you with regular construction updates leading up to settlement.