We are pleased to advise the project is progressing well, with the ground floor concrete slab was completed yesterday (30.07.18). Ramp to the basement to complete today and tomorrow. Level 1 concrete slab is currently being formed up with the first concrete pour to occur at the end of this week or early next week. All apartment joinery has begun production and the next month will see brickwork and blockwork beginning as the structure rises.