Construction update
Work has been continuing onsite and great progress has been made.
So far the restricted numbers on site have not caused any delays to the current program.
Works completed so far are:
- Bulk excavation has been completed.
- Prepared pilling platform has been done.
- Shortcrete shoring walls have been completed.
- In ground services complete.
The basement and ground floor slabs are due to start within the next month.
Completion at this stage is still anticipated for Q3 2022 subject to Government Restrictions