Construction is progressing on site with a small delay in getting lift shaft walls to site. The level 1 external and internal walls have now all been erected.
Load bearing walls will be core filled with concrete week commencing 19th November followed by services rough in and PT/reo installation.
The current program sees the level 2 slab being poured week commencing 26th November