The installation of the car stacker system has now commenced after a shipping delay so activity is now back on track.
Construction on site is generally proceeding well and the contractor has advised that completion is likely to be the third week in May.
The next two weeks will see the exterior of the building complete except for the ground floor retail tenancies and external paving etc.
We will provide a further update in two weeks.