Please find below update from the developer for Centrepiece Residences (formerly known as Duet) at 801 Centre Road, Bentleigh East:
The Centrepiece Residences development is underway, with construction progressing well on site. The builder has completed the guide wall system and is currently installing the basement retention system, with 92 of the 525 contiguous piles installed to date.
With some luck with the weather, we should have the basement retention system complete towards the end of September. This will allow the large bulk of excavation to commence.
We have also seen solid progress with the major authority services diversion works and connection works. The sewer line has been successfully diverted around the site, with these works completed recently on the 3rd of August.
The stormwater connection works have also commenced, with the completion of this expected in September. The build time for this project is approximately 18 months with practical completion due for early 2020.