We are pleased to advise all purchasers of the current construction progress across all levels at Hamptons.

  • Overall
    • Cladding near completion
    • Windows installed
    • Roof complete
    • Lift installed
    • Tower crane dismantled
  • L1
    • Kitchens installed
    • Tiling complete
  • L2
    • Tiling beginning
    • First coat of paint on
  • L3
    • Waterproofing complete
    • Floor preparation underway
  • L4
    • Plastering complete
    • Door frames installed

We will provide further updates as the project progresses.