We are pleased to advise all purchasers of the current construction progress across all levels at Hamptons.
- Overall
- Cladding near completion
- Windows installed
- Roof complete
- Lift installed
- Tower crane dismantled
- L1
- Kitchens installed
- Tiling complete
- L2
- Tiling beginning
- First coat of paint on
- L3
- Waterproofing complete
- Floor preparation underway
- L4
- Plastering complete
- Door frames installed
We will provide further updates as the project progresses.