We are pleased to advise the current construction status for Knoxia Apartments is as follows. Completion is still on track for Oct/Nov 2018.

Concrete Structure
 Lift Core 90%

Townhouse
Townhouse Framing 55%

Services
Basement Rough In 50%
Ground Rough In 100%
Level 1 Rough In 50%
Level 2 Rough in 30%
Level 3 Rough in 15%

Finishes
Wall Linings to Ground 100%
Ceiling Grid to Ground 100%
Wall Linings to Level 1 50%
Wall Framing to Level 2 100%
Wall Framing to Level 3 50%

Blockwork
Structural Blockwork 95%
Planter boxes 40%

Windows
Ground Floor Windows & Glazing 95%
Level 1 Window Frames & Glazing 70%
Level 2 Window Frames 100%