Welcome to the October update for Latrobe Place.

Current status of works onsite are:

• The lift is now in operation
• Services rough in is complete.
• Joinery is complete from Ground to Level 4
• Painting is up to Level 3.

At this stage the anticipated construction completion of your apartment is on track for February 2020. This is subject to favourable conditions or unforeseen delays.

We will ensure to keep you updated as construction progresses.

Please do not hesitate to contact Katrina on 03 8582 8975 or email katrina@settlement-solutions.com.au if you have any queries about your upcoming settlement.