Please find below the latest update from the developer for Rima:


We are now ready for final inspections at Rima.

Please note due to occupational health and safety, no person will be granted access without being pre-registered.

In relation to the programme, the status is as follows:

Programme

The key programme items are as follows:

Stage                                      Status

  1. Site set up works                     Completed
  2. Bulk excavation                        Completed
  3. Basement works                      Completed
  4. Structure works                       Completed
  5. Services rough in                     Completed
  6. Window glazing                        Completed
  7. Facade cladding                       Completed
  8. Internal fit out works                Completed
  9. Finishing works                        Completed
  10. Title registration                       Lodged
  11. Occupancy permit
  12. Ready to settle

 

Access Times for Purchaser Inspections

Access times available are strictly as follows by pre-registration only. We have allowed 15 minute intervals for each booking i.e. 9.00am, 9.15am, 9.30am etc:

Times Available:                       Mon 2 July to Fri 6 July                       8.00am to 4.30pm

 

Pre Registration Process

All apartments must be pre-registered individually otherwise access will be denied.

There is only one inspection allowed per apartment, so please ensure any representatives required are present at the appointment i.e. building inspectors, real estate agents etc.

Registration process is as follows:

  • All registrations must be made in writing with Jessica by email at jhamra@blueearth.com.au
  • Inspection requests must include the following information prior to being pre-registered:
  1. Purchaser name
  2. Name of the representative inspecting
  3. Booking confirmation email address
  4. Booking confirmation mobile phone number
  5. Apartment no to be inspected
  6. Preferred inspection time option 1
  7. Preferred inspection time option 2
  • Once the request has been received, Kim will confirm by email the booking, or recommend an alternative time.
  • On site, Kim will induct the purchaser/s and/or representatives, and walk them through the apartment.

Please note, no access will be granted if the specific apartment is not pre-registered.

All purchaser/s and/or representatives are required to arrive 10 minutes early for registration.

The meeting point and parking is at the site office located on Lygon Street. Please ensure ample time is allowed as street parking is very limited.

 

Settlement Date

Settlement is anticipated for 15 July 2018.

We will keep you updated as we get closer to this date.

 

Contact Person Onsite
Kim Velardi is your dedicated contact person for all matters relating to pre settlement inspections and settlement.