We are please to share an update on some of the latest construction progress at Stanley & Roden. All hands are on deck with both external and internal teams working fervently towards the finish line. 

Apartments/Internal 

  • Works in Progress:
    • Timber Flooring
    • Painting
    • Fit Off – Bathrooms & Kitchens
    • Joinery & Stone

EXTERNAL & COMMON AREAS

  • Main Entry being constructed
  • External Balconies 90% completed
  • External Façade 90% completed
  • Corridors being fitted off
  • Lifts being installed

As you can see we are not far away from construction completion which is expected end of April, with settlements in mid-late May. We look forward to bring you further updates as the time comes.