We are pleased to advise you that construction is continuing to progress well with anticipated completion for third quarter 2019
The above is subject to favourable conditions or unforeseen delays.
Current status of works onsite are:
• Level 1 & 2 window frames to apartments installed, with Level 3 currently being procured for installation.
• Internal plastering is underway to all levels.
• Joinery procurement underway.
• Once the balance of the roof is completed, then the lift installation can commence.