1060 Carnegie is progressing well with settlement anticipated for October 2019. Over the last few months the following work has been carried out:
- Completion of level 3 suspended slab
- Level 4, Pour 2 suspended slab underway
- Continued installation of Precast Panels up to level 3
- Strip out of lower levels commenced for continued high level services installation